Showing posts with label Contract 885. Show all posts
Showing posts with label Contract 885. Show all posts

Sunday, July 5, 2026

CCL6 Preview

4 July 2026 - A view of all 3 Circle Line stage 6 stations seen during the preview open house.

The Circle Line stage 6 (CCL6) preview was held today to allow members of the public to familiarise themselves with the 3 new stations being added to the line. Free rides on the sector were held as part of the public preview. If you haven't heard, SG MRT Construction (SGMC) is holding a short contest where you'll be able to win credits at online shops such as knackstop and Play-E_hobbies. Find out more about SGMC's CCL6 contest here. The contest closes on 13 July, so you still have time to submit an entry after the sector opens on 12 July to participate. Let's now recap a little about the 3 stations along CCL6.

Monday, May 18, 2026

CCL6 - A snapshot in May 2026

Overview of CCL6 contracts 882 to 886 as at mid-May 2026.
Top (L - R): CC30 - Keppel, CC31 - Cantonment
Bottom (L - R): CC32 - Prince Edward Road, Contract 886 cut & cover tunnels

The long awaited missing segment of the Circle Line (CCL) - phase 6 - is about to open on 12 July 2026, with a preview event on 4 July 2026 (hoorah?). Finally, there will be an end to the perpetual question from literal commuters "Why is it called the Circle Line when it is not a circle?". Before then, we catch up with the progress at the three stations and one cut & cover tunnel contract to see how much work is left to be completed before preview & opening days. If you weren't excited enough for the new phase, this post may just help with that.

Saturday, March 21, 2026

CCL6 - A snapshot in February 2026

28 February 2026 - An overview of the progress at 3 stations along the CCL6.

With a few more months to go till the sixth stage of the Circle Line (CCL) is due to open, we check in on progress in the middle of Q1 to see how far the stations have come along. Most of the exits have since been installed with the public transport logo caplet sign and station name signs have been appearing at the various exits. Find out more after the jump.

Friday, December 19, 2025

Year-end Spotlight: Contract 885 - Prince Edward Road

Date unknown - A view of one of the Circle Line platforms at Prince Edward Road station.
Source: LinkedIn

To wrap up the end of the year, we're doing a short "Spotlight" series for the Circle Line Stage 6 (CCL6). In this series, we'll look at the progress made at the various CCL6 stations through the course of the year. Explore our other two posts so far on:

To close off our Spotlight series on CCL6, here's one final update for the progress made at Prince Edward Road station through 2025!


Saturday, October 25, 2025

CCL6 - A snapshot in October 2025

Station exits clad - check. Station structures painted - check. LED train arrival timing boards installed - check. Lights on - check! Station name signs - che... Oops! These are some of the items that have been marked off at the various stage 6 stations along the Circle Line's stage 6 (CCL6). Since September, the rest of the line has undergone early closures & late openings to commence the process of integrating the extension with the rest of the loop.

Saturday, July 5, 2025

CCL6 - A snapshot in June 2025

An overview of the 3 stations under CCL6 in June 2025.

With the Circle Line stage 6 (CCL6) section targeted for completion in the first half of 2026, we took the opportunity to check in on progress made on the 3 new stations along the 4km link. Works at the three stations are in the semi-final stages, with structural works since completed and installation of architectural finishings underway. Commuter facilities such as sheltered bus stops and pick-up/drop-off points are being constructed to support connectivity at the stations. Join us as we take a better look at all the progress made thus far after the jump.

Friday, February 14, 2025

CCL6 - A snapshot in February 2025

Aerial views of the 4 civil contracts along the main line section of the project in early
February 2025.
Top (L - R): CC30 - Keppel, CC31 - Cantonment
Bottom (L - R): CC32 - Prince Edward Road, Contract 886

With the Circle Line stage 6 (CCL6) due to open by the first half of 2026, we're about a year and a half away from the section's completion. Most of the stations' exits have had the roof structures installed and works were transitioning towards the completion of architectural, mechanical & electrical components. We take a closer look at the progress made at the various stations and sites along the project after the jump.

Sunday, November 3, 2024

CCL6 - A snapshot in October 2024

Looks like it has been some time since we made an update on Circle Line stage 6 (CCL6). Since our last update the most significant milestone would be the decommissioning of the temporary staging area for trackworks - more on that later. The various stations also have seen installation of escalators completed at 8 of the eligible exits, while the remaining exit will feature lift-only access. 

Thursday, September 12, 2024

CCL6 - A snapshot in August 2024

An overview of the 4 sites helping to close the Circle Line loop as of August 2024.

Over August 2024, progress at the Circle Line 6 sites has seen work commence or continue on the roof of 7 of the 9 station exits. At this point, escalators had been installed in 7 of the 8 exits requiring their use as well. Additionally, noise barriers had begun to be taken down at Prince Edward Road, following similar works at Keppel before. More details after the jump.

Friday, August 9, 2024

CCL6 - A snapshot in July 2024

A view of the 4 main line contracts for Circle Line's Stage 6 as of end-July 2024.
Top (L - R) : CC30 - Keppel, CC31 - Cantonment
Bottom (L - R) : CC32 - Prince Edward Road, Contract 886 - Cut & Cover tunnels

Works for the Circle Line (CCL)'s Stage 6 main line continues to advance. In July, headway was made through the installation of escalators at Keppel station, the casting of roof slabs for Exits 1 & 2 at Cantonment station and the installation of metal roof frames at Prince Edward Road station. Over at the site of the cut & cover tunnels, work continued ahead of the eventual reinstatement of the roads in the vicinity.

Tuesday, May 28, 2024

C885 - Prince Edward Road update May 2024

 

5 May 2024 - An aerial view of the Prince Edward Road station.

In the three months since our last visit to Prince Edward Road station, the escalators have been installed at the two station exits. The ventilation shaft and cooling tower buildings have also made progress with most of the structures completed. We take a quick look at the progress made over the past 3 months in this post.

Sunday, May 12, 2024

CCL6 - A snapshot in May 2024

 

5 May 2024 - An overview of the street level structures at Keppel station.

5 May 2024 - An aerial view of the Cantonment station worksite.

5 May 2024 - An aerial view of the Prince Edward Road station site.

5 May 2024 - A view of the backfilling & reinstatement works underway along the cut & cover
tunnel section between Prince Edward Road & Marina Bay stations.

It's been a while since we caught up with the progress being made over at the Circle Line 6 stations. As such, we're bring you an early update on the goings on in the early part of May, since our last update on the section was in February.

Monday, March 4, 2024

C885 - Prince Edward Road update February 2024

 

11 February 2024 - A view of the concrete structure of Exit 1 seen from Shenton Way.

Works at Prince Edward Road station have been progressing with more of the surface structures of the station becoming visible. Eventually, there will be approximately 3 ancillary buildings for ventilation & cooling towers, in addition to the station's 2 exits. In addition, there is also a mid-tunnel emergency exit along Keppel Road that has since taken shape. This exit would allow for evacuation from the stacked bored tunnels that run between Prince Edward Road and Cantonment stations in the event of an emergency. There are similar exits located along the Circle Line, such as on either side of the Kallang Basin and near Promenade before the line crosses over Marina Bay.

Friday, December 22, 2023

CCL6 year-end update 2023

 

Contract 882's Keppel station site.
Top : 27 April 2023
Bottom : 9 December 2023

Contract 883's Cantonment station site.
Top : 30 December 2022
Bottom : 9 December 2023

Contract 885's Prince Edward Road station site along Shenton Way.
Top : 4 August 2023
Bottom : 9 December 2023

Contract 886's cut & cover tunnel sites.
Top : 27 April 2023
Bottom : 9 December 2023

It has been a big year for the Circle Line 6 (CCL6) project with the station structures of the 3 new stations now substantially complete. We take a look back at the progress made over the year, comparing the sites as of Q4 to the end of 2022 or earlier in 2023. Do head on after the jump for pictures.

Wednesday, December 13, 2023

CCL6 Newsletter 2023

 


Today, the Land Transport Authority (LTA) released the fifth Circle Line 6 newsletter. In this edition, maps featuring the stations renumbered exits were included in. Several small general updates are also provided within. In summary, station structural works are substantially completed with the works now shifting towards the construction of station exits at street level, the architectural components and mechanical installations.

You can read the newsletter here.

This is a blog-only post.

Tuesday, October 24, 2023

C885 - Prince Edward Road update October 2023

 

14 October 2023 - An aerial view of the Prince Edward Road station site.

Recently the SGMC team visited the Westin Hotel and took in a bit of a view of the downtown area. We had the opportunity to admire the views of Prince Edward Road. It seems that they have since completed the station roof slab and covered up most of the underground structures. Some surface-level elements are now becoming more apparent. But we'll let the pictures do the talking.

Tuesday, August 15, 2023

C885 - Prince Edward Road pictorial update

 

5 August 2023 - A view of the Prince Edward Road station site.

In early August, we managed to get some incredible views of the Prince Edward Road station site from the Westin Hotel's lobby at level 32. Overlooking the western downtown area, the lobby provided the perfect vantage point. Here's our pictorial update for the site as of early-August.

Tuesday, June 6, 2023

C885 - Prince Edward Road update Q2 2023

 

27 April 2023 - A view of the western end of the station box where the launch shaft used to be
covered with an acoustic shed to minimise noise pollution from tunnel works.
Image by Seloloving.

With the Circle Line (CCL) stage 6 being only 3 stations in length, this is the final update for Q2 of 2023 for this extension project. Once again, Seloloving has kindly provided us with these images for our use in the update - thank you and very much appreciated.

Monday, December 19, 2022

C885 - Prince Edward Road 2022 year-end update

 

21 November 2022 - A view of the excavation pit along Shenton Way.

It's been a while since we dropped by Prince Edward Road to check on progress. Things are coming along, but there is not much visible changes at street level. The work site is still filled with machinery performing their various tasks. There are no openings visible yet for station exits, ventilation buildings or cooling towers.

Tuesday, September 27, 2022

Elusive Prince Edward Road

14 September 2022 - A view of the Prince Edward Road
station construction site.

Wow, is it hard to get a shot of this station. Unless you're up on a double decker bus on the expressway, there doesn't seem to be much you can capture of it. So that's what we did to try to get a shot of this elusive station.