| 28 February 2026 - An overview of the progress at 3 stations along the CCL6. |
With a few more months to go till the sixth stage of the Circle Line (CCL) is due to open, we check in on progress in the middle of Q1 to see how far the stations have come along. Most of the exits have since been installed with the public transport logo caplet sign and station name signs have been appearing at the various exits. Find out more after the jump.
CC30 - Keppel (Contract 882)
In a nutshell: External station name signs were present at Exits 2 and 3, although none can be seen within the exits themselves. The station is essentially completed, with minor working remaining till it can be handed over to the public transport operator.
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
CC31 - Cantonment (Contract 883)
In a nutshell: Station name signs were visible at Exits 3 and 4, including the interior. Exit 1 had the public transport logo caplet since installed, although the station name sign could not be seen yet. Along the pedestrian side walks, installation works were underway for the covered linkways connecting to various facilities such as residential blocks and industrial distriparks.
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
CC32 - Prince Edward Road (Contract 885)
In a nutshell: Station name signs could not be found at either of the two exits, although Exit 2 did have the public transport logo caplet installed. Of the three stations, this one appeared to have the most remaining work to be completed.
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
 |
| 28 February 2026 |
The clock is ticking down till the day when the section of line opens, with signage installation works progressing along the rest of the line.
 |
New 2020/TEL-era signage gradually being installed across existing CCL stations. Images by @stormfire_transport |
We eagerly await the official announcement of the line's eventual opening, with several milestones still to be achieved - handover to public transport operator, open house & final opening.