Sunday, November 3, 2024

CCL6 - A snapshot in October 2024

Looks like it has been some time since we made an update on Circle Line stage 6 (CCL6). Since our last update the most significant milestone would be the decommissioning of the temporary staging area for trackworks - more on that later. The various stations also have seen installation of escalators completed at 8 of the eligible exits, while the remaining exit will feature lift-only access. 

Thursday, September 12, 2024

CCL6 - A snapshot in August 2024

An overview of the 4 sites helping to close the Circle Line loop as of August 2024.

Over August 2024, progress at the Circle Line 6 sites has seen work commence or continue on the roof of 7 of the 9 station exits. At this point, escalators had been installed in 7 of the 8 exits requiring their use as well. Additionally, noise barriers had begun to be taken down at Prince Edward Road, following similar works at Keppel before. More details after the jump.

Friday, August 9, 2024

CCL6 - A snapshot in July 2024

A view of the 4 main line contracts for Circle Line's Stage 6 as of end-July 2024.
Top (L - R) : CC30 - Keppel, CC31 - Cantonment
Bottom (L - R) : CC32 - Prince Edward Road, Contract 886 - Cut & Cover tunnels

Works for the Circle Line (CCL)'s Stage 6 main line continues to advance. In July, headway was made through the installation of escalators at Keppel station, the casting of roof slabs for Exits 1 & 2 at Cantonment station and the installation of metal roof frames at Prince Edward Road station. Over at the site of the cut & cover tunnels, work continued ahead of the eventual reinstatement of the roads in the vicinity.

Tuesday, June 4, 2024

C886 - Cut & Cover tunnels update May 2024

 

5 May 2024 - An overview of the temporary staging area for trackworks and the tunnels linking
to Marina Bay station.

The last contract along the Circle Line 6 (CCL6) mainline is contract 886 for the construction of cut & cover tunnels between Prince Edward Road and Marina Bay stations. Work here has been swiftly completed with the backfilling works done. Trackworks are also progressing well within the Temporary Staging Area (TSA), located at the turnback tunnel.

Tuesday, May 28, 2024

C885 - Prince Edward Road update May 2024

 

5 May 2024 - An aerial view of the Prince Edward Road station.

In the three months since our last visit to Prince Edward Road station, the escalators have been installed at the two station exits. The ventilation shaft and cooling tower buildings have also made progress with most of the structures completed. We take a quick look at the progress made over the past 3 months in this post.

Tuesday, May 21, 2024

C883 - Cantonment update May 2024

 

 5 May 2024 - An aerial view of the Cantonment station work site with the platform canopies of
the old railway station fully reinstated to their original positions.

In the three months since our last visit to Cantonment station, there have been several changes. First of all, the platform canopies for the former railway station's platforms have been moved back into their original positions entirely. Secondly, the cooling tower structure is taking place with the metal frame for the louvres and roof put in place. And thirdly, the street-level surface structures of the various exits are beginning to take shape. We delve into the progress made in greater detail in this post.

Monday, May 13, 2024

C882 - Keppel update May 2024

5 May 2024 - An aerial view of the Keppel station site.

 Three months since we last checked in at Keppel station, things have progressed - as they rightly should. Backfilling works of the station site were completed with several of the street level surface structures now visible. Noise barriers near Exits 1 and 2 have also been taken down, now that the noisier works have been completed. The disappearance of these barriers allows closer looks at the station's construction as work on the exits progress.

Sunday, May 12, 2024

CCL6 - A snapshot in May 2024

 

5 May 2024 - An overview of the street level structures at Keppel station.

5 May 2024 - An aerial view of the Cantonment station worksite.

5 May 2024 - An aerial view of the Prince Edward Road station site.

5 May 2024 - A view of the backfilling & reinstatement works underway along the cut & cover
tunnel section between Prince Edward Road & Marina Bay stations.

It's been a while since we caught up with the progress being made over at the Circle Line 6 stations. As such, we're bring you an early update on the goings on in the early part of May, since our last update on the section was in February.

Sunday, March 10, 2024

Contract 883 - Cantonment update February

 

15 February 2024 - Exit 2 as of mid-February.

More sections of the station are beginning to take shape with the surface structures pushing through. The station achieved basic structural completion (BSC) in the middle of 2023, with the exits likely to follow this coming year. Check on after the jump for more pictures!

Monday, March 4, 2024

C885 - Prince Edward Road update February 2024

 

11 February 2024 - A view of the concrete structure of Exit 1 seen from Shenton Way.

Works at Prince Edward Road station have been progressing with more of the surface structures of the station becoming visible. Eventually, there will be approximately 3 ancillary buildings for ventilation & cooling towers, in addition to the station's 2 exits. In addition, there is also a mid-tunnel emergency exit along Keppel Road that has since taken shape. This exit would allow for evacuation from the stacked bored tunnels that run between Prince Edward Road and Cantonment stations in the event of an emergency. There are similar exits located along the Circle Line, such as on either side of the Kallang Basin and near Promenade before the line crosses over Marina Bay.

Tuesday, February 20, 2024

C882 - Keppel update February 2024

 

11 February 2024 - A view eastwards along Keppel Road.

11 February 2024 - More permanent structures can now be seen at the surface level.

It has been a month now since work to "Close the Circle" by connecting tunnels and tracks from Keppel to HarbourFront stations has begun. While temporary changes to the service patterns of the main line were implemented, work continues to make progress over at Contract 882's Keppel station site. We take a look at how the site has changed since we last checked in at the end of 2023.

Wednesday, January 17, 2024

Upcoming temporary CCL service pattern changes 20 Jan - 24 May 2024

 

11 January 2024 - A banner at Buona Vista station informing passengers about the upcoming
temporary service changes.

Its less than a week away to the upcoming temporary Circle Line (CCL) service pattern changes which will commence this Saturday (20 January 2024). What are the changes? Why are the changes needed? And what are the works being done that necessitate these changes? We'll delve into these questions in this post, more after the jump.