With the Circle Line stage 6 (CCL6) due to open by the first half of 2026, we're about a year and a half away from the section's completion. Most of the stations' exits have had the roof structures installed and works were transitioning towards the completion of architectural, mechanical & electrical components. We take a closer look at the progress made at the various stations and sites along the project after the jump.
Friday, February 14, 2025
Sunday, November 3, 2024
CCL6 - A snapshot in October 2024
Looks like it has been some time since we made an update on Circle Line stage 6 (CCL6). Since our last update the most significant milestone would be the decommissioning of the temporary staging area for trackworks - more on that later. The various stations also have seen installation of escalators completed at 8 of the eligible exits, while the remaining exit will feature lift-only access.
Thursday, September 12, 2024
CCL6 - A snapshot in August 2024
![]() |
An overview of the 4 sites helping to close the Circle Line loop as of August 2024. |
Over August 2024, progress at the Circle Line 6 sites has seen work commence or continue on the roof of 7 of the 9 station exits. At this point, escalators had been installed in 7 of the 8 exits requiring their use as well. Additionally, noise barriers had begun to be taken down at Prince Edward Road, following similar works at Keppel before. More details after the jump.
Friday, August 9, 2024
CCL6 - A snapshot in July 2024
Works for the Circle Line (CCL)'s Stage 6 main line continues to advance. In July, headway was made through the installation of escalators at Keppel station, the casting of roof slabs for Exits 1 & 2 at Cantonment station and the installation of metal roof frames at Prince Edward Road station. Over at the site of the cut & cover tunnels, work continued ahead of the eventual reinstatement of the roads in the vicinity.
Tuesday, June 4, 2024
C886 - Cut & Cover tunnels update May 2024
5 May 2024 - An overview of the temporary staging area for trackworks and the tunnels linking to Marina Bay station. |
The last contract along the Circle Line 6 (CCL6) mainline is contract 886 for the construction of cut & cover tunnels between Prince Edward Road and Marina Bay stations. Work here has been swiftly completed with the backfilling works done. Trackworks are also progressing well within the Temporary Staging Area (TSA), located at the turnback tunnel.
Sunday, May 12, 2024
CCL6 - A snapshot in May 2024
5 May 2024 - An overview of the street level structures at Keppel station. |
5 May 2024 - An aerial view of the Cantonment station worksite. |
![]() |
5 May 2024 - An aerial view of the Prince Edward Road station site. |
5 May 2024 - A view of the backfilling & reinstatement works underway along the cut & cover tunnel section between Prince Edward Road & Marina Bay stations. |
It's been a while since we caught up with the progress being made over at the Circle Line 6 stations. As such, we're bring you an early update on the goings on in the early part of May, since our last update on the section was in February.
Friday, December 22, 2023
CCL6 year-end update 2023
![]() |
Contract 882's Keppel station site. Top : 27 April 2023 Bottom : 9 December 2023 |
![]() |
Contract 883's Cantonment station site. Top : 30 December 2022 Bottom : 9 December 2023 |
![]() |
Contract 885's Prince Edward Road station site along Shenton Way. Top : 4 August 2023 Bottom : 9 December 2023 |
![]() |
Contract 886's cut & cover tunnel sites. Top : 27 April 2023 Bottom : 9 December 2023 |
It has been a big year for the Circle Line 6 (CCL6) project with the station structures of the 3 new stations now substantially complete. We take a look back at the progress made over the year, comparing the sites as of Q4 to the end of 2022 or earlier in 2023. Do head on after the jump for pictures.
Wednesday, December 13, 2023
CCL6 Newsletter 2023
Today, the Land Transport Authority (LTA) released the fifth Circle Line 6 newsletter. In this edition, maps featuring the stations renumbered exits were included in. Several small general updates are also provided within. In summary, station structural works are substantially completed with the works now shifting towards the construction of station exits at street level, the architectural components and mechanical installations.
You can read the newsletter here.
This is a blog-only post.
Wednesday, November 1, 2023
C886 - C&C Tunnels & Trackworks update October 2023
![]() |
14 October 2023 - An overview of the contract 886 site. |
Besides getting a great view of Prince Edward Road station, the team also enjoyed great views of the cut & cover tunnels linking Prince Edward Road and Marina Bay stations. This also includes a section of tunnels splitting off the main line known as the turnback tunnels. It is here that the trackworks contractor is given a site to work from, known as the Temporary Staging Area (TSA).
Sunday, August 20, 2023
C886 - C&C Tunnels & Trackworks in progress
![]() |
4 August 2023 - Trackwork Staging Area (TSA) at the turnback siding. |
The recent visit to the Westin Hotel not only gave great views of Prince Edward Road station, but also of the cut & cover tunnels linking to Marina Bay station as well. Being built under contract 886, the tunnels will also feature a turnback siding, from where trackworks are taking place.
Tuesday, June 13, 2023
C886 - Cut & Cover tunnels + Trackwork preparation
![]() |
5 June 2023 - A view of the contract 886 cut & cover turnback tunnel site along Park Street. |
Structural works at contract 886 appear to be almost done with the site being handed over to the trackworks contractor. Known as a temporary staging area (TSA), this will form the base for trackworks to be carried out. Through the duration of the track installation work, some gantry cranes and other support equipment may be used.
Wednesday, December 21, 2022
C886 - C&C Tunnels 2022 year-end update
![]() |
25 November 2022 - A view of the cut & cover tunnels seen from Marina Bay station Exit 5. |
![]() |
25 November 2022 - A close up view of the cut & cover tunnel work site. The retaining wall is visible. |
Friday, September 30, 2022
C886 - C&C tunnels at Marina Bay
![]() |
14 September 2022 - A view of the contract 886 work sites for both the main line & turn back tunnels. |
Contract 886 is for the construction of cut & cover (C&C) tunnels for Circle Line 6 at the Marina Bay area. This contract consists of 2 sections - the main line section and the turnback tunnel section. The tracks at Prince Edward Road (PER) station are in a stacked configuration, thus as they head eastwards to Marina Bay station, the tracks split into two directions. One set known as the main line tunnels, turns southwards to connect to the existing Marina Bay station while another set turns eastwards to end just before Shenton Way station on the Thomson-East Coast Line. This second set is known as the turn back tunnels and will serve to allow trains terminating at PER to reverse directions and commence their return journey at the correct level (as PER is of a stacked platform configuration, hence the tracks are on different levels).
Monday, August 8, 2022
CCL6 Newsletters by LTA
![]() |
Issue 1 of the CCL6 newsletter by LTA. Source: LTA |
Did you know that the Land Transport Authority (LTA) has been releasing several newsletters on the Circle Line 6 (CCL6) project since 2019? Well, neither did we! Nonetheless, we managed to get the digital copies of the 4 newsletters produced to date.
Monday, July 30, 2018
Circle Line 6 Project Information Centre
Recently Minister for Transport Mr. Khaw Boon Wan shared a post introducing the Circle Line 6 Project Information Centre (PIC) which was officially opened. The Project Information Centre is located along Spottiswoode Road in front of the former Tanjong Pagar Railway Station and is open to the public on a walk-in basis, unlike some other centres which require prior bookings and arrangements (for example the Thomson-East Coast Line stage 3 PIC at Orchard station).
![]() |
The Circle Line 6 Project Information Centre. |
Wednesday, February 17, 2016
Pre-qualification
![]() |
Pre-qualification for Circle Line stage 6 civil contracts by LTA |