Wednesday, June 26, 2019

June 2019 - Keppel station progress

Contact 882 is for the construction of Keppel station and bored tunnels between HarbourFront and Cantonment stations. Since our last update in February, works have progressed significantly at both ends of the station.

25 May 2019 - Excavation begins at the eastern launch shaft, for tunnels towards
Cantonment station.
2 June 2019 - Excavation completed till base of capping beam level.
17 June 2019 - Rebar skeleton in place for concrete pouring and casting.

Monday, June 24, 2019

June 2019 - Prince Edward Road station progress

Prince Edward Road station is located in an extremely tight location bounded by Shenton Way to the west, the Marina Coastal Expressway to the south and the Bestway building to the north-east. Several religious buildings dot the site, making it a tough fit to construct a station in the location while being able to maneuver machinery about the site.

21 May 2019 - An aerial view of the Prince Edward Road station site.
Source: Zaw Myo Latt

Wednesday, June 19, 2019

Kim Chuan depot expansion: Road diversion

Contract 821A for the expansion of Kim Chuan depot has been in progress for some time. Excavation works have commenced at the site which is bordered by Bartley Road East and Hougang Avenue 3, located north of the existing depot site.

26 November 2018 - Western end of the Kim Chuan depot extension.
9 June 2019 - Western end of the Kim Chuan depot extension.