Station exits clad - check. Station structures painted - check. LED train arrival timing boards installed - check. Lights on - check! Station name signs - che... Oops! These are some of the items that have been marked off at the various stage 6 stations along the Circle Line's stage 6 (CCL6). Since September, the rest of the line has undergone early closures & late openings to commence the process of integrating the extension with the rest of the loop.
Circle Line 6 Construction
Closing the Circle. Bringing the construction updates to you.
Saturday, October 25, 2025
Saturday, July 5, 2025
CCL6 - A snapshot in June 2025
![]() |
| An overview of the 3 stations under CCL6 in June 2025. |
With the Circle Line stage 6 (CCL6) section targeted for completion in the first half of 2026, we took the opportunity to check in on progress made on the 3 new stations along the 4km link. Works at the three stations are in the semi-final stages, with structural works since completed and installation of architectural finishings underway. Commuter facilities such as sheltered bus stops and pick-up/drop-off points are being constructed to support connectivity at the stations. Join us as we take a better look at all the progress made thus far after the jump.
Friday, March 14, 2025
CCL6 - Signage preview & Feedback
Free this weekend? Looking for a weekend activity? The Land Transport Authority (LTA) is holding a preview for wayfinding signage ahead of deployment along the Circle Line (CCL) when the loop closes. LTA is seeking for your feedback on these signages ahead of deployment. On 14 to 17 March (Friday to Monday), the CCL platform B at Promenade station will be host to some of these signages. Do drop by if you're free to take a look and provide LTA with your views on the new signage for the full loop.
Friday, February 14, 2025
CCL6 - A snapshot in February 2025
With the Circle Line stage 6 (CCL6) due to open by the first half of 2026, we're about a year and a half away from the section's completion. Most of the stations' exits have had the roof structures installed and works were transitioning towards the completion of architectural, mechanical & electrical components. We take a closer look at the progress made at the various stations and sites along the project after the jump.
Sunday, November 3, 2024
CCL6 - A snapshot in October 2024
Looks like it has been some time since we made an update on Circle Line stage 6 (CCL6). Since our last update the most significant milestone would be the decommissioning of the temporary staging area for trackworks - more on that later. The various stations also have seen installation of escalators completed at 8 of the eligible exits, while the remaining exit will feature lift-only access.
Thursday, September 12, 2024
CCL6 - A snapshot in August 2024
![]() |
| An overview of the 4 sites helping to close the Circle Line loop as of August 2024. |
Over August 2024, progress at the Circle Line 6 sites has seen work commence or continue on the roof of 7 of the 9 station exits. At this point, escalators had been installed in 7 of the 8 exits requiring their use as well. Additionally, noise barriers had begun to be taken down at Prince Edward Road, following similar works at Keppel before. More details after the jump.
Friday, August 9, 2024
CCL6 - A snapshot in July 2024
Works for the Circle Line (CCL)'s Stage 6 main line continues to advance. In July, headway was made through the installation of escalators at Keppel station, the casting of roof slabs for Exits 1 & 2 at Cantonment station and the installation of metal roof frames at Prince Edward Road station. Over at the site of the cut & cover tunnels, work continued ahead of the eventual reinstatement of the roads in the vicinity.






