Tuesday, May 28, 2024

C885 - Prince Edward Road update May 2024

 

5 May 2024 - An aerial view of the Prince Edward Road station.

In the three months since our last visit to Prince Edward Road station, the escalators have been installed at the two station exits. The ventilation shaft and cooling tower buildings have also made progress with most of the structures completed. We take a quick look at the progress made over the past 3 months in this post.

Tuesday, May 21, 2024

C883 - Cantonment update May 2024

 

 5 May 2024 - An aerial view of the Cantonment station work site with the platform canopies of
the old railway station fully reinstated to their original positions.

In the three months since our last visit to Cantonment station, there have been several changes. First of all, the platform canopies for the former railway station's platforms have been moved back into their original positions entirely. Secondly, the cooling tower structure is taking place with the metal frame for the louvres and roof put in place. And thirdly, the street-level surface structures of the various exits are beginning to take shape. We delve into the progress made in greater detail in this post.

Monday, May 13, 2024

C882 - Keppel update May 2024

5 May 2024 - An aerial view of the Keppel station site.

 Three months since we last checked in at Keppel station, things have progressed - as they rightly should. Backfilling works of the station site were completed with several of the street level surface structures now visible. Noise barriers near Exits 1 and 2 have also been taken down, now that the noisier works have been completed. The disappearance of these barriers allows closer looks at the station's construction as work on the exits progress.

Sunday, May 12, 2024

CCL6 - A snapshot in May 2024

 

5 May 2024 - An overview of the street level structures at Keppel station.

5 May 2024 - An aerial view of the Cantonment station worksite.

5 May 2024 - An aerial view of the Prince Edward Road station site.

5 May 2024 - A view of the backfilling & reinstatement works underway along the cut & cover
tunnel section between Prince Edward Road & Marina Bay stations.

It's been a while since we caught up with the progress being made over at the Circle Line 6 stations. As such, we're bring you an early update on the goings on in the early part of May, since our last update on the section was in February.