Sunday, March 10, 2024

Contract 883 - Cantonment update February

 

15 February 2024 - Exit 2 as of mid-February.

More sections of the station are beginning to take shape with the surface structures pushing through. The station achieved basic structural completion (BSC) in the middle of 2023, with the exits likely to follow this coming year. Check on after the jump for more pictures!

Monday, March 4, 2024

C885 - Prince Edward Road update February 2024

 

11 February 2024 - A view of the concrete structure of Exit 1 seen from Shenton Way.

Works at Prince Edward Road station have been progressing with more of the surface structures of the station becoming visible. Eventually, there will be approximately 3 ancillary buildings for ventilation & cooling towers, in addition to the station's 2 exits. In addition, there is also a mid-tunnel emergency exit along Keppel Road that has since taken shape. This exit would allow for evacuation from the stacked bored tunnels that run between Prince Edward Road and Cantonment stations in the event of an emergency. There are similar exits located along the Circle Line, such as on either side of the Kallang Basin and near Promenade before the line crosses over Marina Bay.