27 April 2023 - A view eastwards of Keppel Road and the station box site. Image by Seloloving. |
The Circle Line is progressing towards final loop closure with the addition of 3 stations along a 4km route between HarbourFront and Marina Bay terminals. Bored tunneling works between the stations have been completed for some time now while work continues on at the stations and cut & cover tunnels at the Marina Bay area. At the surface level, it is difficult to tell how much progress has been achieved. However by estimates, it is anticipated that the three stations should achieve basic structure completion some time this year with the exits to follow thereafter. Join us as we explore the progress under contract 882 for Keppel station.
Keppel station will be the largest of the 3 stations under stage 6 of the Circle Line. The station will feature 4 tracks, which include 2 cripple sidings parallel to the station platform. On the eastern end of the station, a future usable space is catered for, extending from the station concourse. It is likely that this space will be developed for future commercial & retail offerings.
27 April 2023 - Street level view along Keppel Road. Image by Seloloving. |
27 April 2023 - A street level view of the work site for an additional exit connected by subway to the main station box. Image by Seloloving. |
Works at the station box site have reached the roof slab level, with several pillars visible at ground level to support future structures above such as covered linkways or station exit roofing. Back filling work had commenced last year and have progressed a little. The decking that was previously located near the site of back filling has since been removed to allow works to proceed.
27 April 2023 - A view of the station box work site from the overhead pedestrian bridge. Image by Seloloving. |
27 April 2023 - Some back filling works are ongoing at the site. Image by Seloloving. |
27 April 2023 - Another view of the station box work site and Keppel Road. Image by Seloloving. |
27 April 2023 Image by Seloloving. |
27 April 2023 - Eastern end of the site. Image by Seloloving. |
27 April 2023 Image by Seloloving. |
27 April 2023 - Remaining decking and struts at the eastern end. Image by Seloloving. |
27 April 2023 Image by Seloloving. |
27 April 2023 Image by Seloloving. |
27 April 2023 Image by Seloloving. |
Over at the site of the exit across from the main station box, concrete casting works are ongoing. Unfortunately due to a lack of vantage points, we are unable to determine the level at which works are being carried out, unlike one of the exits at Cantonment station.
27 April 2023 - Work site for the additional exit outside the distripark. Image by Seloloving. |
27 April 2023 - Concrete casting works ongoing. Image by Seloloving. |
Works are progressing slowly but surely ahead of the line's commissioning in 2026. We would like to thank Seloloving for helping to provide all the images in today's post. If you have images to share or would like to let us know about the progress of works in your area, do let us know through our various channels. We're always happy to feature and credit you.
No comments:
Post a Comment