25 May 2019 - Excavation begins at the eastern launch shaft, for tunnels towards Cantonment station. |
2 June 2019 - Excavation completed till base of capping beam level. |
17 June 2019 - Rebar skeleton in place for concrete pouring and casting. |
The eastern launch shaft has since been dug to the first level where the rebar skeleton is put in place ahead of the concrete pour. This will give the launch shaft a rigid horizontal bracing and allow the diaphragm walls to retain the surrounding earth as excavation progresses further down.
25 May 2019 |
2 June 2019 - Casting works on-going for drainage diversion over the work site. |
2 June 2019 - A view of the main work site area. |
25 May 2019 - King posts waiting to be driven into the ground |
2 June 2019 - King posts waiting to be driven in to the ground at the work site. |
17 June 2019 - Visibly less crowded work site |
17 June 2019 |
25 May 2019 - Excavation next to west launch shaft beginning. |
2 June 2019 - First level of struts in place, following excavation. |
25 May 2019 - One of the two gantry cranes at the western launch shaft set up. |
2 June 2019 |
2 June 2019 - Both gantry cranes standing at the western launch shaft |
17 June 2019 - Noise enclosure being built around the western launch shaft. |
17 June 2019 - Ground improvement works ahead of tunneling works commencement. |
According to LTA, tunnelling works to HarbourFront have begun as of 25 July.