Wednesday, June 19, 2019

Kim Chuan depot expansion: Road diversion

Contract 821A for the expansion of Kim Chuan depot has been in progress for some time. Excavation works have commenced at the site which is bordered by Bartley Road East and Hougang Avenue 3, located north of the existing depot site.

26 November 2018 - Western end of the Kim Chuan depot extension.
9 June 2019 - Western end of the Kim Chuan depot extension.

Wednesday, April 10, 2019

February 2019 - Cantonment station progress

Contract 883 is for the construction of Cantonment station along the Circle Line stage 6. The awarded contractor is China State Construction Engineering Co (CSCEC), who are also part of a joint venture with Nishimatsu Corporation on adjoining contract 882. The contract for Cantonment station involves construction of only the station structure with no tunneling works included.

11 February 2019 - An aerial view of the Cantonment station construction site.

Thursday, February 14, 2019

February 2019 - Keppel station progress

Contract 882 is for the construction of Keppel station and tunnels for Circle Line stage 6. The assigned contractor is a joint venture between China State Construction Engineering Co (CSCEC) & Nishimatsu. Both contractors in this joint venture have been involved in MRT construction locally before with projects on the Downtown and Circle Lines.

11 February 2019 - Project details on a signboard near one of the site access gates.

Monday, July 30, 2018

Circle Line 6 Project Information Centre


Recently Minister for Transport Mr. Khaw Boon Wan shared a post introducing the Circle Line 6 Project Information Centre (PIC) which was officially opened. The Project Information Centre is located along Spottiswoode Road in front of the former Tanjong Pagar Railway Station and is open to the public on a walk-in basis, unlike some other centres which require prior bookings and arrangements (for example the Thomson-East Coast Line stage 3 PIC at Orchard station).

The Circle Line 6 Project Information Centre.

Wednesday, February 17, 2016

Pre-qualification

Pre-qualification for Circle Line stage 6 civil contracts by LTA
On Monday, the Land Transport Authority released the pre-qualification tender for 5 civil contracts for the construction of Circle Line stage 6. The 5 contracts involve the construction of the Kim Chuan depot extension and Keppel, Cantonment and Prince Edward stations along with the connecting tunnel structures.

Sunday, November 1, 2015

Stations revealed

Rail System Map with included Circle Line stage 6.
Source - LTA
Last week the Ministry of transport revealed the final locations of the 3 stations that made up Circle Line stage 6. The three stations are tentatively called Keppel, Cantonment and Prince Edward for their proximity to roads with the same names.

Thursday, August 20, 2015

CCL6 Route and Station Predictions

It has been a year since Stage 4 and 5 of TEL was announced. Judging by annual schedules of LTA events and the looming deadline of the completion of several MRT lines and extensions by 2025, we expect that CCL6 will be announced in August or September this year. Like what we have done for TSL (later renamed as TEL Stage 1-3) and TEL Stage 4-5, here are our predictions for CCL6.



Overall CCL6 Route Map