Tuesday, June 4, 2024

C886 - Cut & Cover tunnels update May 2024

 

5 May 2024 - An overview of the temporary staging area for trackworks and the tunnels linking
to Marina Bay station.

The last contract along the Circle Line 6 (CCL6) mainline is contract 886 for the construction of cut & cover tunnels between Prince Edward Road and Marina Bay stations. Work here has been swiftly completed with the backfilling works done. Trackworks are also progressing well within the Temporary Staging Area (TSA), located at the turnback tunnel.